Cost Estimation
Phasing of Activities
Input Requirement |
Data Source |
Remarks |
Designing- for every five year till design year, comprising of all SWM components |
Primary analysis |
|
Broad cost estimate under different components with phasing
Input Requirement |
Data Source |
Remarks |
Cost estimate for each phase comprising of all elements |
Estimation on the basis of Market rate/Schedule of rates/rate analysis |
|
Capital investment Requirement for each Phase for Ghaziabad |
All Amount in Rs. Million |
||||||||||
S. No. |
Item |
2011-15 |
2016-20 |
2021-25 |
2026-30 |
Total |
|||||
A |
Collection and Transport Equipment |
No. |
Amt. |
No |
Amt. |
No. |
Amt. |
No. |
Amt. |
No. |
Total Amt. |
A |
Total |
3,681 |
224 |
4,508 |
174.6 |
5,713 |
335.3 |
6,820 |
396.3 |
20,722 |
1,130.20 |
B |
Processing Plant |
||||||||||
B1 |
Equipment |
|
|
|
|
|
|
|
|
|
|
B1 |
Total |
|
81 |
- |
- |
15 |
16.5 |
|
|
33 |
97.5 |
B2 |
Infrastructure works |
|
60 |
- |
- |
- |
- |
- |
- |
|
60 |
Rs 20.0 million for :M4lthree sites |
|||||||||||
B |
Total (B1+B2) |
|
141 |
|
|
|
16.5 |
|
|
|
157.5 |
C |
Land Fill Site |
||||||||||
C1 |
Total |
15 |
41.7 |
|
|
9 |
13.2 |
|
|
24 |
54.9 |
C2 |
Land fill site development |
-1 |
494.3 |
- |
- |
- |
- |
- |
- |
- |
494.3 |
334,056 |
|||||||||||
sqm cell area @ Rs 1300 |
|||||||||||
(2) other |
|||||||||||
LS |
|||||||||||
Rs 20.0 mn for each site |
|||||||||||
C2 |
Total |
|
494.3 |
- |
- |
- |
- |
- |
- |
|
494.3 |
C |
Total(C1+C2) |
|
536 |
|
|
|
13.2 |
|
|
|
549.2 |
D |
Construction of ward offices |
LS |
40 |
|
|
|
|
|
|
|
40 |
@ Rs 0.5 million each for 80 wards |
|||||||||||
E |
Construction of Transfer station @ 0.1 million for each zone |
LS |
50 |
|
|
|
|
|
|
|
50 |
|
Grand Total (A+B+C+D+E) |
|
991 |
|
174.6 |
|
365 |
|
3963 |
|
1,926.90 |
Capital replacement plan- based on their life cycle
Input Requirement |
Data Source |
Remarks |
Primary analysis |
Primary analysis |
|
Equipment will require replacement after end of economic life |
||
Primary collection equipment shall be replaced after 5 years |
||
Transport vehicles after 10 years |
||
Heavy machines like bulldozer/Landfill compactors after 20 years |
Total capital cost estimation
Input Requirement |
Data Source |
Remarks |
Primary analysis -Sum of all the components |
|
Addition of contingencies and allowance to total cost estimation
Input Requirement |
Data Source |
Remarks |
(1)5% annual increment as price escalation on current rate(2) 3% as physical contingency(3) 3% for DSC and project preparation (4) 1% each for social, environmental, IEC and capacity building (5) special provision for utility shifting and any other visible expenditure on project specific basis |
Primary analysis |