Phasing of Activities

Input Requirement

Data Source

Remarks

Designing-  for every five year till design year, comprising of all SWM components

Primary analysis

 

go top

Broad cost estimate under different components with phasing

Input Requirement

Data Source

Remarks

Cost estimate for each phase comprising of all elements

Estimation on the basis of Market rate/Schedule of rates/rate analysis

 

Capital investment Requirement for each Phase for Ghaziabad

All Amount in Rs. Million

S. No.

Item

2011-15

2016-20

2021-25

2026-30

Total

A

Collection and Transport Equipment

No.

Amt.

No

Amt.

No.

Amt.

No.

Amt.

No.

Total Amt.

A

Total

3,681

224

4,508

174.6

5,713

335.3

6,820

396.3

20,722

1,130.20

B

Processing Plant

B1

Equipment

 

 

 

 

 

 

 

 

 

 

B1

Total

 

81

-

-

15

16.5

 

 

33

97.5

B2

Infrastructure works

 

60

-

-

-

-

-

-

 

60

 Rs 20.0 million for :M4lthree sites

B

Total (B1+B2)

 

141

 

 

 

16.5

 

 

 

157.5

C

Land Fill Site

C1

Total

15

41.7

 

 

9

13.2

 

 

24

54.9

C2

Land fill site development

-1

494.3

-

-

-

-

-

-

-

494.3

             334,056

sqm cell area @ Rs 1300

(2) other

 LS

Rs 20.0 mn for each site

C2

Total

 

494.3

-

-

-

-

-

-

 

494.3

C

Total(C1+C2)

 

536

 

 

 

13.2

 

 

 

549.2

D

Construction of ward offices

LS

40

 

 

 

 

 

 

 

40

@ Rs 0.5 million each for 80 wards

E

Construction of Transfer station @ 0.1 million for each zone

LS

50

 

 

 

 

 

 

 

50

 

Grand Total (A+B+C+D+E)

 

991

 

174.6

 

365

 

3963

 

1,926.90

go top

Capital replacement plan- based on their life cycle

Input Requirement

Data Source

Remarks

Primary analysis

Primary analysis

Equipment will require replacement after end of economic life

Primary collection equipment shall be replaced after 5 years

Transport vehicles after 10 years

Heavy machines like bulldozer/Landfill compactors after 20 years

go top

Total capital cost estimation

Input Requirement

Data Source

Remarks

Primary analysis -Sum of all the components

 

go top

Addition of contingencies and allowance to total cost estimation

Input Requirement

Data Source

Remarks

(1)5% annual increment as price escalation on current rate(2) 3% as physical contingency(3) 3% for DSC and project preparation (4) 1% each for social, environmental, IEC and capacity building (5) special provision for utility shifting and any other visible expenditure on project specific basis

Primary analysis

go top